WEEK 19
WEEK 19 - Daily Report
DAY 1 - 19 Feb 2024
1. TASK 10 (Block Transaction by DN MID TID)
1. TASK 10 (Block Transaction by DN MID TID)
- Study the design specs, solutions.
- Do the development in the program source files.
- Learn how to prepare the test message (ISO 8583) for the task.
DAY 2 - 20 Feb 2024
1. TASK 10 (Block Transaction by DN MID TID)
- Do the development in the program source files.
- Do the testing to test the new test message after add new data element for this task.
DAY 3 - 21 Feb 2024
1. TASK 10 (Block Transaction by DN MID TID)
- Complete preparing the new test message after add new data element successfully.
- Do the development in the program source files.
- Face some problem to retrieve the new data element in the program.
DAY 4 - 22 Feb 2024
1. TASK 10 (Block Transaction by DN MID TID)
- Facing the same problem to retrieve the new data element in the program.
DAY 5 - 23 Feb 2024
1. TASK 10 (Block Transaction by DN MID TID)
- Do the development in the program source files.
- Successfully retrieve the new data element in the program.
- Create a new function to do the checking using the new data retrieve from the test message.
- Successfully create the new function to do the checking.